RENCANA ANGGARAN BIAYA ( PEKERJAAN MEKANIKAL ELEKTRIKAL )

No. Deskripsi Pekerjaan Volume  Satuan   Harga Satuan   Jumlah Harga 
             
A.   PEKERJAAN LANTAI 01        
             
A.1 INSTALASI TITIK LAMPU DAN STOP KONTAK        
  1 instalasi lampu TL      4.00 ttk  Rp        450,000.00  Rp    1,800,000.00
  2 instalasi lampu downlight   20.00 ttk  Rp        175,000.00  Rp    3,500,000.00
  3 instalasi lampu PLC      5.00 ttk  Rp        125,000.00  Rp        625,000.00
  4 instalasi stop kontak      8.00 ttk  Rp        250,000.00  Rp    2,000,000.00
          JUMLAH A.1.  PEK. INSTALASI TITIL LAMPU & STOP KONTAK  Rp    7,925,000.00
A.2 INSTALASI AIR KOTOR        
  1 Jaringan pipa 4 Inch   20.00 m1  Rp          80,000.00  Rp    1,600,000.00
  2 Jaringan pipa 3 Inch   20.00 m2  Rp          70,000.00  Rp    1,400,000.00
  3 jaringan pipa 1.5 Inch   15.00 m3  Rp          50,000.00  Rp        750,000.00
          JUMLAH A.2.  PEK. INSTALASI AIR KOTOR  Rp    3,750,000.00
A.3 INSTALASI AIR BERSIH        
  1 Jaringan Pipa 3/4 Inch   40.00 m1  Rp          45,000.00  Rp    1,800,000.00
          JUMLAH A.3.  PEK. INSTALASI AIR BERSIH  Rp    1,800,000.00
A.4 INSTALASI AIR HUJAN        
  1 Saluran Air hujan   35.00 m1  Rp        275,000.00  Rp    9,625,000.00
          JUMLAH A.4.  PEK. INSTALASI AIR HUJAN  Rp    9,625,000.00
          JUMLAH  PEKERJAAN LANTAI 01  Rp  23,100,000.00
B   PEKERJAAN LANTAI 02        
             
B.1 INSTALASI TITIK LAMPU DAN STOP KONTAK        
  1 Instalasi Lampu Downlight   15.00 ttk  Rp        175,000.00  Rp    2,625,000.00
  2 Instalasi Stop kontak      6.00 ttk  Rp        250,000.00  Rp    1,500,000.00
          JUMLAH B.1.  PEK. INSTALASI TITIL LAMPU & STOP KONTAK  Rp    4,125,000.00
B.2 INSTALASI AIR HUJAN        
  1 Instalasi Air hujan   15.00 m1  Rp          80,000.00  Rp    1,200,000.00
          JUMLAH B.2.  PEK. INSTALASI AIR HUJAN  Rp    1,200,000.00
          JUMLAH  PEKERJAAN LANTAI 02  Rp    5,325,000.00
C   PEKERJAAN LANTAI 3        
C.1 INSTALASI WATER TORN        
    Instalasi watertorn      2.00 unit  Rp    3,500,000.00  Rp    7,000,000.00
          JUMLAH C.1.  PEK. INSTALASI AIR HUJAN  Rp    7,000,000.00
          JUMLAH  PEKERJAAN LANTAI 03  Rp    7,000,000.00
D   PEKERJAAN LAIN-LAIN        
           
  1 Box Panel Listrik      1.00 unit  Rp    7,500,000.00  Rp    7,500,000.00
  2 Instalasi Listrik Outdoor      1.00 unit  Rp    5,000,000.00  Rp    5,000,000.00
          JUMLAH D.  PEK. LAIN-LAIN  Rp  12,500,000.00
          JUMLAH  PEKERJAAN LAIN-LAIN  Rp  12,500,000.00
GRAND TOTAL (Belum Termasuk Jasa dan Pajak)  Rp  47,925,000.00