No. | Deskripsi Pekerjaan | Volume | Satuan | Harga Satuan | Jumlah Harga | |
A. | PEKERJAAN LANTAI 01 | |||||
A.1 | INSTALASI TITIK LAMPU DAN STOP KONTAK | |||||
1 | instalasi lampu TL | 4.00 | ttk | Rp 450,000.00 | Rp 1,800,000.00 | |
2 | instalasi lampu downlight | 20.00 | ttk | Rp 175,000.00 | Rp 3,500,000.00 | |
3 | instalasi lampu PLC | 5.00 | ttk | Rp 125,000.00 | Rp 625,000.00 | |
4 | instalasi stop kontak | 8.00 | ttk | Rp 250,000.00 | Rp 2,000,000.00 | |
JUMLAH A.1. PEK. INSTALASI TITIL LAMPU & STOP KONTAK | Rp 7,925,000.00 | |||||
A.2 | INSTALASI AIR KOTOR | |||||
1 | Jaringan pipa 4 Inch | 20.00 | m1 | Rp 80,000.00 | Rp 1,600,000.00 | |
2 | Jaringan pipa 3 Inch | 20.00 | m2 | Rp 70,000.00 | Rp 1,400,000.00 | |
3 | jaringan pipa 1.5 Inch | 15.00 | m3 | Rp 50,000.00 | Rp 750,000.00 | |
JUMLAH A.2. PEK. INSTALASI AIR KOTOR | Rp 3,750,000.00 | |||||
A.3 | INSTALASI AIR BERSIH | |||||
1 | Jaringan Pipa 3/4 Inch | 40.00 | m1 | Rp 45,000.00 | Rp 1,800,000.00 | |
JUMLAH A.3. PEK. INSTALASI AIR BERSIH | Rp 1,800,000.00 | |||||
A.4 | INSTALASI AIR HUJAN | |||||
1 | Saluran Air hujan | 35.00 | m1 | Rp 275,000.00 | Rp 9,625,000.00 | |
JUMLAH A.4. PEK. INSTALASI AIR HUJAN | Rp 9,625,000.00 | |||||
JUMLAH PEKERJAAN LANTAI 01 | Rp 23,100,000.00 | |||||
B | PEKERJAAN LANTAI 02 | |||||
B.1 | INSTALASI TITIK LAMPU DAN STOP KONTAK | |||||
1 | Instalasi Lampu Downlight | 15.00 | ttk | Rp 175,000.00 | Rp 2,625,000.00 | |
2 | Instalasi Stop kontak | 6.00 | ttk | Rp 250,000.00 | Rp 1,500,000.00 | |
JUMLAH B.1. PEK. INSTALASI TITIL LAMPU & STOP KONTAK | Rp 4,125,000.00 | |||||
B.2 | INSTALASI AIR HUJAN | |||||
1 | Instalasi Air hujan | 15.00 | m1 | Rp 80,000.00 | Rp 1,200,000.00 | |
JUMLAH B.2. PEK. INSTALASI AIR HUJAN | Rp 1,200,000.00 | |||||
JUMLAH PEKERJAAN LANTAI 02 | Rp 5,325,000.00 | |||||
C | PEKERJAAN LANTAI 3 | |||||
C.1 | INSTALASI WATER TORN | |||||
Instalasi watertorn | 2.00 | unit | Rp 3,500,000.00 | Rp 7,000,000.00 | ||
JUMLAH C.1. PEK. INSTALASI AIR HUJAN | Rp 7,000,000.00 | |||||
JUMLAH PEKERJAAN LANTAI 03 | Rp 7,000,000.00 | |||||
D | PEKERJAAN LAIN-LAIN | |||||
1 | Box Panel Listrik | 1.00 | unit | Rp 7,500,000.00 | Rp 7,500,000.00 | |
2 | Instalasi Listrik Outdoor | 1.00 | unit | Rp 5,000,000.00 | Rp 5,000,000.00 | |
JUMLAH D. PEK. LAIN-LAIN | Rp 12,500,000.00 | |||||
JUMLAH PEKERJAAN LAIN-LAIN | Rp 12,500,000.00 | |||||
GRAND TOTAL (Belum Termasuk Jasa dan Pajak) | Rp 47,925,000.00 | |||||