No. | Deskripsi Pekerjaan | Volume | Satuan | Harga Satuan | Jumlah Harga | |
I. | PEKERJAAN PERSIAPAN | |||||
I.1 | PEKERJAAN PEMBERSIHAN | |||||
1 | Pembersihan Lahan Tepak Bangunan | 1.00 | ls | Rp 1,000,000.00 | Rp 1,000,000.00 | |
2 | Bouwplank | 1.00 | ls | Rp 1,250,000.00 | Rp 1,250,000.00 | |
3 | Pengukuran Bangunan | 1.00 | ls | Rp 750,000.00 | Rp 750,000.00 | |
I.2 | PEKERJAAN BANGUNAN SEMENTARA | |||||
1 | Barak Pekerja | 1.00 | ls | Rp 2,250,000.00 | Rp 2,250,000.00 | |
2 | Gudang Material | 1.00 | ls | Rp 1,750,000.00 | Rp 1,750,000.00 | |
I.3 | PEKERJAAN MOBILISASI | |||||
1 | Mobilisasi-Demobilisasi Peralatan | 1.00 | ls | Rp 4,750,000.00 | Rp 4,750,000.00 | |
2 | Mobilisasi-Demobilisasi SDM | 1.00 | ls | Rp 3,500,000.00 | Rp 3,500,000.00 | |
3 | Mobilisasi matrial | 120.00 | hari | Rp 150,000.00 | Rp 18,000,000.00 | |
I.4 | PEKERJAAN OPERASIONAL | |||||
1 | K3 | 1.00 | ls | Rp 2,375,000.00 | Rp 2,375,000.00 | |
2 | Instalasi dan alat Listrik Kerja | 1.00 | ls | Rp 3,750,000.00 | Rp 3,750,000.00 | |
3 | Instalasi dan alat Air Kerja | 1.00 | ls | Rp 3,500,000.00 | Rp 3,500,000.00 | |
JUMLAH I. PEKERJAAN PERSIAPAN | Rp 42,875,000.00 | |||||
II. | PEKERJAAN LANTAI 01 | |||||
II.1 | PEKERJAAN TANAH | |||||
1 | Galian Tanah untuk Footplate | 61.20 | m3 | Rp 35,000.00 | Rp 2,142,000.00 | |
2 | Galian Tanah untuk Pondasi | 8.00 | m3 | Rp 35,000.00 | Rp 280,000.00 | |
3 | Urugan Tanah Kembali | 51.90 | m3 | Rp 35,000.00 | Rp 1,816,500.00 | |
4 | Urugan Tanah Peninggian Peil | 69.30 | m3 | Rp 35,000.00 | Rp 2,425,500.00 | |
5 | Urugan Pasir 10 cm | 9.27 | m3 | Rp 88,944.47 | Rp 824,515.24 | |
6 | Lantai Kerja 5 cm | 6.87 | m3 | Rp 807,404.59 | Rp 5,546,869.52 | |
II.2 | PEKERJAAN FOOTPLATE | |||||
1 | F1 (1,2 x 1,2) | 8.76 | M3 | Rp 3,700,250.00 | Rp 32,423,440.63 | |
2 | F2 (0,8 x 0,8) | 3.00 | M3 | Rp 3,700,250.00 | Rp 11,100,750.00 | |
II.3 | PEKERJAAN TIE BEAM | |||||
1 | TB1 (0,3 x 0,45) | 11.21 | M3 | Rp 3,700,250.00 | Rp 41,461,301.25 | |
2 | TB2 (0,2 x 0,35) | 1.61 | M3 | Rp 3,700,250.00 | Rp 5,957,402.50 | |
II.4 | PEKERJAAN KOLOM | |||||
1 | K1 (0,35 x 0,35) | 10.62 | M3 | Rp 3,700,250.00 | Rp 39,299,430.19 | |
2 | K2 (0,2 x 0,2) | 0.78 | M3 | Rp 3,700,250.00 | Rp 2,886,195.00 | |
II.5 | PEKERJAAN BALOK LT.2 | |||||
1 | Balok B1 (0,2 x 0,3) | 3.63 | m3 | Rp 3,700,250.00 | Rp 13,431,907.50 | |
2 | Balok B2 (0,3 x 0,45) | 9.65 | m3 | Rp 3,700,250.00 | Rp 35,716,663.13 | |
3 | Balok BA (0,2 x 0,35) | 0.92 | m3 | Rp 3,700,250.00 | Rp 3,419,031.00 | |
4 | Lisplank Beton | 0.72 | m3 | Rp 3,700,250.00 | Rp 2,664,180.00 | |
II.6 | PEKERJAAN PLAT LANTAI | |||||
1 | Plat LT.2 | 10.40 | m3 | Rp 3,700,250.00 | Rp 38,497,401.00 | |
II.7 | PEKERJAAN PLAT TANGGA & BORDES | |||||
1 | Plat Tangga, Kolom Tangga & Bordes Type A | 2.26 | m3 | Rp 3,700,250.00 | Rp 8,344,063.75 | |
JUMLAH II. PEKERJAAN LANTAI 01 | Rp 248,237,150.69 | |||||
III. | PEKERJAAN LANTAI 02 | |||||
III.1 | PEKERJAAN KOLOM | |||||
1 | K1 (0,35 x 0,35) | 8.23 | m3 | Rp 3,700,250.00 | Rp 30,460,458.00 | |
III.2 | PEKERJAAN BALOK LT.3 | |||||
1 | Balok B2 (0,3 x 0,45) | 10.10 | m3 | Rp 3,944,000.00 | Rp 39,826,512.00 | |
2 | Balok BA (0,2 x 0,35) | 0.69 | m3 | Rp 3,944,000.00 | Rp 2,733,192.00 | |
4 | Lisplank Beton | 0.48 | m3 | Rp 3,944,000.00 | Rp 1,893,120.00 | |
III.3 | PEKERJAAN PLAT lantai 3 | |||||
1 | Plat LT.3 | 8.40 | m3 | Rp 3,944,000.00 | Rp 33,129,600.00 | |
III.4 | PEKERJAAN PLAT TANGGA & BORDES | |||||
1 | Plat Tangga, Kolom Tangga & Bordes Type A | 2.26 | m3 | Rp 3,944,000.00 | Rp 8,893,720.00 | |
JUMLAH II. PEKERJAAN LANTAI 02 | Rp 116,936,602.00 | |||||
IV. | PEKERJAAN LANTAI 03 | |||||
IV.1 | PEKERJAAN KOLOM | |||||
1 | Kolom K3 (0,25 x 0,25) | 0.25 | m3 | Rp 3,944,000.00 | Rp 986,000.00 | |
IV.2 | PEKERJAAN BALOK LT.3 | |||||
1 | Balok B2 (0,3 x 0,45) | 1.19 | m3 | Rp 3,944,000.00 | Rp 4,685,472.00 | |
JUMLAH II. PEKERJAAN LANTAI 03 | Rp 5,671,472.00 | |||||
JUMLAH TOTAL (Belum Termasuk Jasa dan Pajak) | Rp 413,720,224.69 |