No. |
Deskripsi
Pekerjaan |
Volume |
Satuan |
Harga Satuan |
Jumlah Harga |
|
|
|
|
|
|
|
I. |
|
PEKERJAAN LANTAI 01 |
|
|
|
|
|
|
|
|
|
|
|
I.1 |
PEKERJAAN TANAH |
|
|
|
|
|
1 |
Galian Tanah untuk Pondasi Batu Kali & Sloof Praktis |
8.00 |
m3 |
Rp
30,000.00 |
Rp 240,000.00 |
|
2 |
Urug Tanah kembali |
6.00 |
m3 |
Rp
15,000.00 |
Rp 90,000.00 |
|
|
|
|
|
JUMLAH I.1. PEKERJAAN
TANAH |
Rp 330,000.00 |
I.2 |
PEKERJAAN BETON NON STRUKTURAL |
|
|
|
|
|
1 |
Kolom Praktis |
2.52 |
m3 |
Rp
3,221,875.00 |
Rp
8,133,623.44 |
|
2 |
Balok Latai |
0.65 |
m3 |
Rp
3,221,875.00 |
Rp
2,078,109.38 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.2. PEKERJAAN
BETON NON STRUKTURAL |
Rp 10,211,732.81 |
I.3 |
PEKERJAAN PASANGAN |
|
|
|
|
|
1 |
Pasang Pondasi Batu Kali |
9.60 |
m3 |
Rp
335,000.00 |
Rp
3,216,000.00 |
|
2 |
Pasang Dinding Batu Bata |
275.94 |
m2 |
Rp
92,500.00 |
Rp
25,524,450.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.3. PEKERJAAN
PASANGAN |
Rp 28,740,450.00 |
I.4 |
PEKERJAAN PENUTUP DINDING |
|
|
|
|
|
1 |
Plesteran & Acian |
551.88 |
m2 |
Rp
47,500.00 |
Rp
26,214,300.00 |
|
2 |
Keramik Dinding |
39.78 |
m2 |
Rp
225,000.00 |
Rp
8,949,375.00 |
|
3 |
Pasang List Keramik Dinding |
21.50 |
m' |
Rp
155,000.00 |
Rp
3,332,500.00 |
|
4 |
Finishing Beton |
68.60 |
m2 |
Rp
35,000.00 |
Rp
2,401,000.00 |
|
|
|
|
|
JUMLAH I.4. PEKERJAAN
PENUTUP DINDING |
Rp 40,897,175.00 |
I.5 |
PEKERJAAN PLAFOND |
|
|
|
|
|
1 |
Pasang Plafond beserta Rangka |
106.75 |
m2 |
Rp
85,000.00 |
Rp
9,073,750.00 |
|
2 |
Pasang List Plafond |
100.00 |
m' |
Rp
17,500.00 |
Rp
1,750,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.5. PEKERJAAN
PLAFOND |
Rp 10,823,750.00 |
I.6 |
PEKERJAAN PENUTUP LANTAI |
|
|
|
|
|
1 |
Pasang Penutup Lantai |
126.95 |
m2 |
Rp
525,000.00 |
Rp
66,648,750.00 |
|
2 |
Pasang Penutup Lantai KM/WC |
22.75 |
m2 |
Rp
275,000.00 |
Rp
6,256,250.00 |
|
3 |
Pasang Plint Lantai |
125.00 |
m' |
Rp
183,750.00 |
Rp
22,968,750.00 |
|
4 |
Pasang Penutup Lantai Tangga dan Bordes |
9.13 |
m2 |
Rp
525,000.00 |
Rp
4,790,625.00 |
|
5 |
Pasang Plint Lantai Tangga dan Bordes |
13.00 |
m' |
Rp
183,750.00 |
Rp
2,387,831.25 |
|
6 |
Stepnosing Anak Tangga |
20.00 |
m' |
Rp
115,000.00 |
Rp
2,300,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.6. PEKERJAAN
PENUTUP LANTAI |
Rp 105,352,206.25 |
I.7 |
PEKERJAAN CAT |
|
|
|
|
|
1 |
Cat Dinding Interior |
275.94 |
m2 |
Rp
27,500.00 |
Rp
7,588,350.00 |
|
2 |
Cat Dinding Exterior |
380.34 |
m2 |
Rp
29,500.00 |
Rp
11,220,030.00 |
|
3 |
Cat Plafond |
106.75 |
m2 |
Rp
27,500.00 |
Rp
2,935,625.00 |
|
4 |
Cat List Plafond |
100.00 |
m' |
Rp
12,500.00 |
Rp
1,250,000.00 |
|
|
|
|
|
JUMLAH I.7. PEKERJAAN
CAT |
Rp 22,994,005.00 |
I.8 |
PEKERJAAN PINTU & JENDELA |
|
|
|
|
|
1 |
Pekerjaan Kusen Jati
6/12 Jati Kw 1 |
126.80 |
m1 |
Rp
225,000.00 |
Rp
28,530,000.00 |
|
2 |
Pekerjaan Pintu Jati |
8.00 |
unit |
Rp
2,500,000.00 |
Rp
20,000,000.00 |
|
3 |
Pekerjaan Jendela kaca bevel bingkai jati |
8.00 |
unit |
Rp
975,000.00 |
Rp
7,800,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.8. PEKERJAAN
PINTU & JENDELA |
Rp 56,330,000.00 |
I.9 |
PEKERJAAN PENGGANTUNG.PENGAIT DAN PENGUNCI |
|
|
|
|
|
1 |
Ensel Pintu 4" |
12.00 |
psg |
Rp
100,000.00 |
Rp
1,200,000.00 |
|
2 |
Ensel jendela 3" |
16.00 |
psg |
Rp
75,000.00 |
Rp
1,200,000.00 |
|
3 |
Lock case termasuk handle pintu |
8.00 |
psg |
Rp
450,000.00 |
Rp
3,600,000.00 |
|
4 |
Handle pintu Utama |
2.00 |
psg |
Rp
1,500,000.00 |
Rp
3,000,000.00 |
|
5 |
Hak angin |
16.00 |
psg |
Rp
50,000.00 |
Rp 800,000.00 |
|
6 |
Door stopper |
8.00 |
pcs |
Rp
150,000.00 |
Rp
1,200,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.9. PEKERJAAN
PENGGANTUNG & PENGUNCI |
Rp 11,000,000.00 |
I.10 |
PEKERJAAN FINISHING KAYU |
|
|
|
|
|
1 |
Finishing Melamin lack clear PU Kusen |
126.80 |
m1 |
Rp
45,000.00 |
Rp
5,706,000.00 |
|
2 |
Finishing Melamin lack clear PU Daun Pintu |
8.00 |
unit |
Rp
425,000.00 |
Rp
3,400,000.00 |
|
3 |
Finishing Melamin lack clear PU Daun Jendela |
16.00 |
unit |
Rp
150,000.00 |
Rp
2,400,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.10.
PEKERJAAN FINISHING KAYU |
Rp 11,506,000.00 |
I.11 |
PEKERJAAN SANITAIR |
|
|
|
|
|
1 |
Closed Jongkok |
2.00 |
unit |
Rp
125,000.00 |
Rp 250,000.00 |
|
2 |
Floor Drain |
6.00 |
unit |
Rp
80,000.00 |
Rp 480,000.00 |
|
3 |
Kran Dinding |
14.00 |
unit |
Rp
175,000.00 |
Rp
2,450,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH I.11.
PEKERJAAN SANITAIR |
Rp 3,180,000.00 |
|
|
|
|
|
JUMLAH PEKERJAAN LANTAI 01 |
Rp
301,365,319.06 |
II. |
|
PEKERJAAN LANTAI 02 |
|
|
|
|
|
|
|
|
|
|
|
II.1 |
PEKERJAAN BETON NON STRUKTURAL |
|
|
|
|
|
1 |
Kolom Praktis |
2.27 |
m3 |
Rp
3,221,875.00 |
Rp
7,307,212.50 |
|
2 |
Balok Latai |
0.96 |
m3 |
Rp
3,221,875.00 |
Rp
3,093,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.1.
PEKERJAAN BETON NON STRUKTURAL |
Rp 10,400,212.50 |
II.2 |
PEKERJAAN PASANGAN |
|
|
|
|
|
1 |
Pasang Dinding Batu Bata |
185.64 |
m2 |
Rp
92,500.00 |
Rp
17,171,700.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.2.
PEKERJAAN PASANGAN |
Rp 17,171,700.00 |
II.3 |
PEKERJAAN PENUTUP DINDING |
|
|
|
|
|
1 |
Plesteran & Acian |
371.28 |
m2 |
Rp
47,500.00 |
Rp
17,635,800.00 |
|
2 |
Finishing Beton |
68.60 |
m2 |
Rp
35,000.00 |
Rp
2,401,000.00 |
|
|
|
|
|
JUMLAH II.3.
PEKERJAAN PENUTUP DINDING |
Rp 20,036,800.00 |
II.4 |
PEKERJAAN PLAFOND |
|
|
|
|
|
1 |
Pasang Plafond beserta Rangka |
70.00 |
m2 |
Rp
85,000.00 |
Rp
5,950,000.00 |
|
2 |
Pasang List Plafond |
44.00 |
m' |
Rp
17,500.00 |
Rp 770,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.4.
PEKERJAAN PLAFOND |
Rp 6,720,000.00 |
II.5 |
PEKERJAAN PENUTUP LANTAI |
|
|
|
|
|
1 |
Pasang Penutup Lantai |
60.00 |
m2 |
Rp
525,000.00 |
Rp
31,500,000.00 |
|
2 |
Pasang Plint Lantai |
59.00 |
m' |
Rp
183,750.00 |
Rp
10,841,250.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.5.
PEKERJAAN PENUTUP LANTAI |
Rp 42,341,250.00 |
II.6 |
PEKERJAAN CAT |
|
|
|
|
|
1 |
Cat Dinding Interior |
185.64 |
m2 |
Rp
27,500.00 |
Rp
5,105,100.00 |
|
2 |
Cat Dinding Exterior |
185.64 |
m2 |
Rp
29,500.00 |
Rp
5,476,380.00 |
|
3 |
Cat Plafond |
70.00 |
m2 |
Rp
27,500.00 |
Rp
1,925,000.00 |
|
4 |
Cat List Plafond |
44.00 |
m' |
Rp
12,500.00 |
Rp 550,000.00 |
|
|
|
|
|
JUMLAH II.6.
PEKERJAAN CAT |
Rp 13,056,480.00 |
II.7 |
PEKERJAAN PINTU & JENDELA |
|
|
|
|
|
1 |
Pekerjaan Kusen Jati
6/12 Jati Kw 1 |
138.45 |
m1 |
Rp
225,000.00 |
Rp
31,151,250.00 |
|
2 |
Pekerjaan Pintu Jati |
- |
unit |
Rp
2,500,000.00 |
Rp - |
|
3 |
Pekerjaan Jendela kaca bevel bingkai jati |
26.00 |
unit |
Rp
975,000.00 |
Rp
25,350,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.7.
PEKERJAAN PINTU & JENDELA |
Rp 56,501,250.00 |
II.8 |
PEKERJAAN PENGGANTUNG.PENGAIT DAN PENGUNCI |
|
|
|
|
|
1 |
Ensel jendela 3" |
26.00 |
psg |
Rp
75,000.00 |
Rp
1,950,000.00 |
|
2 |
Hak angin |
26.00 |
psg |
Rp
50,000.00 |
Rp
1,300,000.00 |
|
|
|
|
|
JUMLAH II.8.
PEKERJAAN PENGGANTUNG & PENGUNCI |
Rp 3,250,000.00 |
II.9 |
PEKERJAAN FINISHING KAYU |
|
|
|
|
|
1 |
Finishing Melamin lack clear PU Kusen |
138.45 |
m1 |
Rp
45,000.00 |
Rp
6,230,250.00 |
|
3 |
Finishing Melamin lack clear PU Daun Jendela |
26.00 |
unit |
Rp
185,000.00 |
Rp
4,810,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.9.
PEKERJAAN FINISHING KAYU |
Rp 11,040,250.00 |
II.11 |
PEKERJAAN WATERPROOFING |
|
|
|
|
|
1 |
Waterproofing Dak Beton |
36.75 |
m2 |
Rp
125,000.00 |
Rp
4,593,750.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH II.11.
PEKERJAAN WATERPROOFING |
Rp 4,593,750.00 |
|
|
|
|
|
JUMLAH PEKERJAAN LANTAI 02 |
Rp
185,111,692.50 |
III. |
|
PEKERJAAN LANTAI 3 |
|
|
|
|
|
|
|
|
|
|
|
III.1 |
PEKERJAAN BETON NON STRUKTURAL |
|
|
|
|
|
1 |
Kolom Praktis |
0.36 |
m3 |
Rp
3,221,875.00 |
Rp
1,159,875.00 |
|
2 |
Balok Ring |
0.66 |
m3 |
Rp
3,221,875.00 |
Rp
2,126,437.50 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.1.
PEKERJAAN BETON NON STRUKTURAL |
Rp 3,286,312.50 |
III.2 |
PEKERJAAN PASANGAN |
|
|
|
|
|
1 |
Pasang Dinding Batu Bata |
25.30 |
m2 |
Rp
95,000.00 |
Rp
2,403,500.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.2.
PEKERJAAN PASANGAN |
Rp 2,403,500.00 |
III.3 |
PEKERJAAN PENUTUP DINDING |
|
|
|
|
|
1 |
Plesteran & Acian |
53.13 |
m2 |
Rp
47,500.00 |
Rp
2,523,675.00 |
|
2 |
Pasang Rooster |
8.80 |
m2 |
Rp
10,000.00 |
Rp 88,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.3.
PEKERJAAN PENUTUP DINDING |
Rp 2,611,675.00 |
III.5 |
PEKERJAAN PENUTUP LANTAI |
|
|
|
|
|
1 |
Screed dan floor hardener |
70.00 |
m2 |
Rp
87,500.00 |
Rp
6,125,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.5.
PEKERJAAN PENUTUP LANTAI |
Rp 6,125,000.00 |
III.6 |
PEKERJAAN CAT |
|
|
|
|
|
1 |
Cat Dinding Interior |
26.57 |
m2 |
Rp
27,500.00 |
Rp 730,537.50 |
|
2 |
Cat Dinding Exterior |
26.57 |
m2 |
Rp
29,500.00 |
Rp 783,667.50 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.6.
PEKERJAAN CAT |
Rp 1,514,205.00 |
III.11 |
PEKERJAAN WATERPROOFING |
|
|
|
|
|
1 |
Waterproofing Lantai |
70.00 |
m2 |
Rp
125,000.00 |
Rp
8,750,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
JUMLAH III.11.
PEKERJAAN WATERPROOFING |
Rp 8,750,000.00 |
III.12 |
PEKERJAAN ATAP |
|
|
|
|
|
1 |
Pasang Roof Drain |
4.00 |
bh |
Rp
200,000.00 |
Rp 800,000.00 |
|
|
|
|
|
JUMLAH III.12.
PEKERJAAN WATERPROOFING |
Rp 800,000.00 |
|
|
|
|
|
JUMLAH PEKERJAAN
LANTAI 03 |
Rp 25,490,692.50 |
IV. |
|
PEKERJAAN LAIN - LAIN |
|
|
|
|
IV.2 |
PEKERJAAN RAILLING |
|
|
|
|
|
1 |
Railling Void |
12.00 |
m1 |
Rp
750,000.00 |
Rp
9,000,000.00 |
|
2 |
Railling tangga |
9.50 |
m1 |
Rp
550,000.00 |
Rp
5,225,000.00 |
|
|
|
|
|
JUMLAH IV.2.
PEKERJAAN RAILLING |
Rp 14,225,000.00 |
IV.3 |
PEKERJAAN FASADE |
|
|
|
|
|
1 |
Ban-banan Fasade |
136.00 |
m1 |
Rp
75,000.00 |
Rp
10,200,000.00 |
|
2 |
Kubah Masjid dari GRC |
1.00 |
bh |
Rp
10,000,000.00 |
Rp
10,000,000.00 |
|
3 |
Plat topi-topi |
17.00 |
unit |
Rp
300,000.00 |
Rp
5,100,000.00 |
|
|
|
|
|
JUMLAH IV.3.
PEKERJAAN FASADE |
Rp 25,300,000.00 |
IV.4 |
PEKERJAAN DRAINAGE |
|
|
|
|
|
1 |
Sumur Air Bersih |
1.00 |
unit |
Rp
5,000,000.00 |
Rp
5,000,000.00 |
|
2 |
Sumur Resapan |
2.00 |
unit |
Rp
1,500,000.00 |
Rp
3,000,000.00 |
|
3 |
Septic Tank |
1.00 |
unit |
Rp
5,000,000.00 |
Rp
5,000,000.00 |
|
4 |
Reservoir |
2.00 |
unit |
Rp
1,000,000.00 |
Rp
2,000,000.00 |
|
|
|
|
|
JUMLAH IV.4.
PEKERJAAN DRAINAGE |
Rp 15,000,000.00 |
|
|
|
|
|
JUMLAH PEKERJAAN LAIN-LAIN |
Rp
54,525,000.00 |
JUMLAH TOTAL
(Belum Termasuk Jasa dan Pajak) |
Rp
566,492,704.06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|